The project formally commenced in July 2013 and is anticipated to be completed by mid 2017.

Given the complexities of the issues that need to be addressed for Ingleside and the iterative nature of the process, delays to the program have unfortunately occurred.



Key Milestones



   

Prior to formal Community Launch of Precinct Plan project

Timing


    Establishment of Project Control Group (PCG)
  Completed - July 2013

    Project Plan (Community Engagement Strategy) & Probity Plan endorsed by PCG
  Completed - July 2013

    Community Engagement Tools for formal launch
  Completed - July 2013

Formal Commencement – Precinct Plan project


    Launch – Information Session
  Completed - July 2013

    Community Information Session
  Completed - Aug 2013

    Ingleside Community Reference Group – Community members selected
  Completed - Sept 2013

Ingleside Precinct Plan Project

Please Note:  The timing will be dependent on the outcome of the results of the Angus Onion Orchid surveys. 


    Appointment of consultants to undertake studies which will provide detailed evidence about issues and constraints and will inform the rezoning
  Completed - Oct 2013

    Commencement of studies to inform precinct planning
  Commenced - Nov 2013

    Ongoing consultation with other government agencies and service providers
  Completed - March 2014

    Enquiry by Design Workshops - Round 1 Workshops
  Completed - March to Oct 2014

    Preparation of potential land use arrangements based on preliminary technical findings
  Commenced - Nov 2014

    Enquiry by Design Workshops - draft Structure Plan
  Completed - Late 2014

    Prepare and refine the draft Structure Plan, draft zoning and development controls based on technical evidence and feedback from our enquiry by design workshops
  Commenced - Late 2014 to late 2015

    Survey for the Angus Onion Orchid
  Completed - Sept/Oct 2015

    Report back to the Ingleside Community Reference Group on the findings
  Completed - 8 Dec 2015
 We are here White_arrow_sq
    Consultation on draft Structure Plan and technical studies before formal exhibition
  December 2016 to February 2017

    Review of submissions
  Following consultation

    Public Exhibition of draft planning controls (including section 94 plan, stautory contols and biodiversity certification package)
  Mid 2017

    Review of submissions
  Following Public Exhibition

  Gazettal of final Precinct Plan
  Late 2017

    Development can begin
  Following Rezoning